Prima Pearl


KONE JumpLift helps to speed up construction work and utilise a building’s hoistway as soon as the first floors of a building have been completed. These construction site lifts are self climbing and have a temporary machine room that moves upwards (jumps) in the hoistway. Once construction work on the building structure is completed, changing to a permanent lift is quick and easy.

We had exciting oportunity to observe “two floors” jump at Prima Pearl which was done within one hour. Complete procedure inclusive of commissionning of the new levels takes up to five hours.

KONE JumpLift 1000 have maximum capacity of 1600 kg and a maximum speed of 2.5 m/s.KONE JumpLift 2000 hve maximum capacity of 4000 kg and a maximum speed of 4.0 m/s.